Can I track the percentage of work completed on a task?

No, we intentionally offer you another way to track your projects. Often when a project plan shows that a task is 90% complete, it means that the person is kind of starting the task. It is sad how widespread this practice is in small and big companies. At the end of the day, this can decrease the level of trust for project management software. To avoid this issue, we offer you a way to split the work into as many simple tasks as necessary and then use a binary system: complete or active (not complete). This approach allows you to have a clear picture of what is done and what is not. It helps you unambiguously know where your projects stand.